Concrete workers from S&S Builders, LLC, of Gillette rolled on toward Sunset Drive Friday on North Federal Boulevard in Riverton. Friday’s concrete pour was in excess of 1,000 cubic yards (100 concrete trucks), the largest one-day pour so far in the two-year, $13.96 million highway improvement project. Work started at 5:30 a.m., and it was completed about 3:15 p.m.

For more updates on the project, follow #RivertonRebuild< Photo above captured by Rood Dog Video Productions

Officially, 955 cubic yards of concrete poured Friday, July 19, on the $13.96 million highway improvement project in Riverton. Crew seated at 5:30 am, wrapped up the pour at 3:15 pm. #rivertonrebuild